Estimating Methodology & Primary Yield Standards
Every takeoff multiplier and bid-margin formula on JobCostMath is documented openly for independent verification.
Verified Formulas
- Quikrete Concrete Yields: 1 cu yd = 27 cu ft; 80 lb bag =
0.60 cu ft(45/yd³); 60 lb =0.45 cu ft(60/yd³); 40 lb =0.30 cu ft(90/yd³). - Roof Pitch Geometry:
Multiplier = sqrt(1 + (Rise/12)²); 1 square = 100 sq ft; architectural shingles = 3 bundles/square; synthetic roll = 1,000 sq ft. - Bulk Landscaping:
Cubic Yards = Area_sqft × Depth_in / 324; hardwood mulch ~0.40 tons/yd³, crushed stone #57 ~1.40 tons/yd³, topsoil ~1.10 tons/yd³. - Contractor Accounting:
Bid = Cost × (1 + Markup);Gross Margin = (Bid − Cost) / Bid = Markup / (1 + Markup);Net Profit = Gross Profit − (Bid × Overhead%).